WEEK -1 THE OLD HOUSE |
||
WEEK 0 CONTRACT, PACKING |
![]() |
|
![]() |
WEEK 1 DEMOLITION |
|
WEEK 2 DEMOLITION |
![]() |
|
WEEK 3 NEW CONCRETE FLOORS |
||
WEEK 4 FRAMING |
||
WEEK 5 FRAMING, ROOF |
||
![]() |
WEEK 6 WALLS |
|
![]() |
WEEK 7 WINDOWS, GARAGE |
![]() |
WEEK 8 FRAMED |
||
![]() |
WEEK 9 DUCTING, GARAGE FLOOR |
|
![]() |
WEEK 10 WIRING, FACING |
![]() |
![]() |
WEEK 11 PLUMBING, INSULATION |
|
![]() |
WEEK 12 STUCCO |
|
![]() |
WEEK 13 DRYWALL, PLASTER |
![]() |
WEEK 14 DOORS, CASING |
![]() |
|
WEEK 15 ROCK FACADE, CLEANUP |
||
WEEK 16 PAINTING |
||
WEEK 17 CABINETS, CLEANUP |
||
![]() |
WEEK 18 CABINETS, LIGHTS ON! |
|
![]() |
WEEK 19 FINISH PAINTING |
|
![]() |
WEEK 20 WALKWAY, |
![]() |
![]() |
WEEK 21 GAS MAIN, DRIVEWAY |
|
WEEK 22 GRANITE, |
||
WEEK 23 TILE |
||
![]() |
WEEK 24 APPLIANCES |
![]() |
WEEK 25 FLOOR |
||
WEEK 26 COMPRESSOR, FIREPLACE |
||
WEEK 27 STAIRWAY, DECK |
||
WEEK 28 BATHROOMs |
||
WEEK 29 PATIO |
![]() |
|
WEEK 30 CARPET |