WEEK BY WEEK

WEEK
-1

THE OLD HOUSE

WEEK
0

CONTRACT, PACKING

WEEK
1

DEMOLITION

WEEK
2

DEMOLITION

WEEK
3

NEW CONCRETE FLOORS

WEEK
4

FRAMING

WEEK
5

FRAMING, ROOF

WEEK
6

WALLS

WEEK
7

WINDOWS, GARAGE

WEEK
8

FRAMED

WEEK
9

DUCTING, GARAGE FLOOR

WEEK
10

WIRING, FACING

WEEK
11

PLUMBING, INSULATION

WEEK
12

STUCCO

WEEK
13

DRYWALL, PLASTER

WEEK
14

DOORS, CASING

WEEK
15

ROCK FACADE, CLEANUP

WEEK
16

PAINTING

WEEK
17

CABINETS, CLEANUP

WEEK
18

CABINETS, LIGHTS ON!

WEEK
19

FINISH PAINTING

WEEK
20

WALKWAY,
DRIVEWAY

WEEK
21

GAS MAIN, DRIVEWAY

WEEK
22

GRANITE,

WEEK
23
TILE
WEEK
24
APPLIANCES
WEEK
25
FLOOR
WEEK
26
COMPRESSOR,
FIREPLACE
WEEK
27
STAIRWAY,
DECK
WEEK
28
BATHROOMs
WEEK
29
PATIO
WEEK
30
CARPET